Sainshand, October 13, 2026 /MONTSAME/. President Khurelsukh Ukhnaa visited Dornogobi aimag on October 12 to inspect the construction of the first oil refinery in Altanshiree soum.
The refinery, a government project in Altanshiree soum, is about 60% complete. Construction has been divided into four phases based on the technical complexity of the facilities, the sequence of work, and the time required for engineering.
Equipment deliveries are underway. A vacuum distillation column manufactured in India was shipped from Mumbai through the Arabian Sea to China’s Tianjin port before being transported by heavy-duty truck to the construction site in Dornogobi aimag. An atmospheric distillation column arrived at the site two months ago.
About 4,500 engineers and technical workers are working around the clock in three shifts to meet the target of commissioning the refinery in 2028. The facility is designed to process 1.5 million tonnes of crude oil annually, meeting 55% of Mongolia’s domestic demand for petroleum products. Its planned annual output includes 824,000 tonnes of diesel fuel, 396,000 tonnes of AI-95 gasoline, 80,000 tonnes of jet fuel, 17,000 tonnes of furnace fuel and 27,000 tonnes of liquefied petroleum gas. The refinery is expected to create 850-900 jobs once it becomes operational.





Prime Minister Uchral: Mother Tongue Is the Spiritual Foundation and a Safeguard of National Independence
President
President Khurelsukh: I Will Bring Those Who Are Defaming Me Before The Relevant Authorities and Have My Honor Restored
Politics EN
BREAKING: President Khurelsukh Hands Over Duties to Clear His Name of Corruption Allegations