Ulaanbaatar, November 12, 2026 /MONTSAME/. Basic infrastructure for Hunnu City is being developed in the Khushig Valley, around Chinggis Khaan International Airport, located 53 km from Ulaanbaatar and 10 km from Zuunmod.
The city is planned to accommodate 150,000 residents and create 80,000 jobs. The development encompasses a free economic zone, leisure and tourism districts, commercial and public services, administrative zones, a university campus, educational and scientific research complexes, trade and wholesale hubs, the international airport, air cargo facilities, and industrial reserve areas.
According to the Public Relations Division of the Ulaanbaatar Governor’s Office, the smart, digitally integrated "Sergelen" substation covering 6.4 hectares has been built and commissioned. Beyond supplying electricity to Hunnu City, the facility serves as a vital transit hub for the regional power grid. Powered by the Songino substation, it bridges power transmission lines connecting the Buuruljuut Power Plant, Sergelen, Gorodok, and other directions. The project involved installing over 400 pieces of equipment integrated with modern digital automation, control, and monitoring systems.
Infrastructure milestones achieved to date include the construction of railway lines serving Hunnu City, with trial operations already underway. A 41.5 km fiber-optic cable network with dedicated conduit structures has been installed. The "Khundii" power substation and the primary flood protection canal have been completed.

Currently, construction of the “Aerocity” Power Substation is 80% complete, while the "Hunnu Eco Heat-2" dual-source thermal plant has reached 40% completion. A reservoir with a capacity of 2,000 cubic meters per day and its associated pipeline networks are 85% complete, while the wastewater treatment plant, designed to process 3,000 cubic meters per day, is 50% complete.