Bayankhoshuu Sub-Center Development Shows Steady Progress
According to officials, infrastructure development within the Bayankhoshuu sub-center has reached 96 percent completion. To date, a 20-unit mixed-use residential building, a kindergarten with capacity for 240 children, a business incubator center, a 50-unit apartment building, and a 35/10 kV substation have been commissioned. Flood protection embankments and landscaping works are complete, while the development of a 2.4-hectare public park is 91 percent finished.