Ulaanbaatar /MONTSAME/ A total of 27 bridges measuring 2427.7m in total will be built as part of the 414.6km Tavantolgoi-Zuunbayan railway construction project under implementation by Mongolian Railway state owned JSC.
On September 7, subcontractor Tuulyn Guur Dalai LLC successfully completed its railway construction on a 132.11m bridge. The company’s has so far honored 98.99 percent of its project commitments, while the bridge construction part of the major railway project is currently 76.81 percent complete.