Rio Tinto caught red-handed
While Rio Tinto has not provided concrete responses to the findings of the independent experts, Rio Tinto started to publicize their position on major global media outlets such as mining.com and financialtimes.com stating that “One of the factors that contributed to the US$1.45 billion cost overrun is the increase in investment costs for Mongolian workers.” In other words, while Rio Tinto initially explained “Cost overruns and project delays were due to ground conditions,” pointing at an inanimate object, they are now blaming their Mongolian workers. Outraged by the statement, the executives of Oyu Tolgoi’s mine workers’ trade union submitted a letter of demand to Kh. Amarjargal, Country Director in charge of Rio Tinto’s operations in Mongolia.